| 24900662 |
false |
|
false |
|
2024-02-09 10:59:39.156 |
| 24915096 |
false |
|
true |
The Industry is required to submit bank gurantee. However the same has not been recieved yet. The industry has been once again requested to submit the compliance of hearing decision within one day, please. |
2024-02-12 10:02:34.347 |
| 24924022 |
false |
|
false |
|
2024-02-12 22:08:49.953 |
| 24924374 |
false |
|
false |
|
2024-02-12 23:24:33.426 |
| 24925424 |
true |
close after approval |
false |
|
2024-02-13 09:48:00.06 |
| 24926145 |
true |
|
false |
|
2024-02-13 10:36:33.346 |
| 24931520 |
false |
|
true |
The competent Authority has sought following clarifications:-
As per agenda, the industry shall generate trade effluent @652 KLD whereas the industry has given proposal for discharge of 189KLD only. What about the remaining effluent. No details has been mentioned regarding the No. Of soft flow machines to be installed by the industry. Permission from ground water authority for extraction of water. No details has been mentioned regarding the quantities of HW to be generated. Status of approved building plans.
Kindly clarify the above points within two days, so as to proceed further in the matter. |
2024-02-13 15:08:26.605 |
| 24931727 |
false |
|
false |
|
2024-02-13 15:16:06.289 |
| 24926192 |
false |
|
true |
Kindly apply CTO under Water Act, 1974 too. |
2024-02-13 10:39:31.819 |
| 25429787 |
true |
|
false |
|
2024-04-16 11:10:30.002 |