
| Id | Approve | Approve Note | Clarification | Clarification Note | Date Created |
|---|---|---|---|---|---|
| 30886222 | false | true | The application of the unit has been scrutinized and observed as under :- (1) The unit has not attached feasibility report of the boiler (8TPH). (2) The layout plan submitted by the unit is not readable. The unit is requested to attach readable copy of the same. The unit is requested to clarify above observations within 03 days to process the case please. | 2026-01-11 18:08:41.396 | |
| 30886245 | false | false | 2026-01-11 18:10:32.794 | ||
| 30886251 | false | false | 2026-01-11 18:11:34.596 | ||
| 30886259 | false | false | 2026-01-11 18:12:05.902 | ||
| 30886303 | false | false | 2026-01-11 18:20:13.188 | ||
| 30886313 | false | false | 2026-01-11 18:22:07.824 | ||
| 30886319 | false | false | 2026-01-11 18:23:04.841 | ||
| 30887050 | false | false | 2026-01-12 00:12:27.828 | ||
| 31372835 | true | false | 2026-03-03 16:41:12.38 | ||
| 31506578 | false | false | 2026-03-18 16:39:09.841 |