The application of the PP was scrutinized and following observations were made:-
1. The PP has required to submit latest CA Certificate including Lease Value. 2. The PP has not submitted permission / approval for establishment / operation of this unit / activity.
3. The PP has required to deposit adequate consent fee including penalty.
4. As per the application form, the commissioning of the unit is stated as February 2023, whereas the rent agreement has been executed on 17.08.2022.
You are requested to clarify the above said observations within 2 days.
|