Id: 20121440
Approve: false
Approve Note:
Clarification: true
Clarification Note: The application of the project proponent has been scrutinized and it was observed as under: 1. The project proponent has not submitted building plan approved from competent person under Factory Act, 1948. You are therefore requested to submit the reply of the above said observations within 3 days.
Date Created: 2022-10-07 10:56:18.546
File Note:
Inspection: false
Inspection Note:
Officer: PPCB114
Reject: false
Reject Note:
Role: RO AEE Piyush Jindal