| Id: | 20440551 |
| Approve: | false |
| Approve Note: | |
| Clarification: | false |
| Clarification Note: | |
| Date Created: | 2022-11-18 22:07:40.423 |
| File Note: | <p>1. Consent granted to the brick kiln was valid upto 30.6.2018. What action is taken after expiry of consent due to non-adoption of zig-zag technology.</p> <p>2. Documents on the basis of which earlier consent was granted on 19.3.2014, are not uploaded.</p> <p>3. Partnership deed is on legal paper, whether it is required to registered in Tehsil office or not. Please clarify.</p> <p>4 Copy of parthership deed dated 21.1.2006 is not attached.</p> |
| Inspection: | false |
| Inspection Note: | |
| Officer: | PPCB038 |
| Reject: | false |
| Reject Note: | |
| Role: | ZO SEE Rajiv Goyal |