| Clarification Note: |
The application submitted by the project proponent has been scrutinized and various discrepancies observed as under:
1. The industry needs to submit CA certificate under three headings i.e. Land & Building, Plant & Machinery and Other fixed assets.
2. The project proponent has submitted completion certificate regarding installation of STP. The project proponent needs to submit capacity of the STP installed within the premises.
3. The project proponent needs to submit brief project report of Apple Resort.
It is requested to clarify regarding the same within 03 days, so as to proceed further in the matter.
|