| File Note: |
<p>1. The validity of consents have been mentioned as 31.07.2022.</p>
<p>2. Mention the quantities of product for which the industry has consents earlier and the quantities for which this application has been applied.</p>
<p>3. Whether the machinery installed by the industry has been verified during visit? Complete details of the machinery installed. </p>
<p>4.If the industry is carrying further expansion, whether NOC applied for it or not? Status of the same.</p>
<p>5.Exisiting ETP installed is adequate for increased production?</p>
<p>6. As per your discussion with EE ZO , proceedings of the hearing have already been issued; incorporate the proceedings and give concrete recommendation in the application. </p>
<p>Reply to the above said observations and resubmit.</p> |