| Id: | 20553526 |
| Approve: | false |
| Approve Note: | |
| Clarification: | true |
| Clarification Note: | The application of the project proponent has been scrutinized and it was observed as under: 1. The project proponent has not deposited consent fee with the application. 2. The project proponent has installed new machinery in the project. The project proponent needs to clarify that any change in the production capacity after installation of new machinery. You are therefore requested to submit the reply of the above said observation within 2 days. |
| Date Created: | 2022-12-02 11:35:24.296 |
| File Note: | |
| Inspection: | false |
| Inspection Note: | |
| Officer: | PPCB114 |
| Reject: | false |
| Reject Note: | |
| Role: | RO AEE Piyush Jindal |