Show ApplicationProcessingDetails

Id: 20568271
Approve: false
Approve Note:
Clarification: true
Clarification Note: The application of the Industry has been scrutinized and it is observed as under: 1. Earlier, the project proponent was granted ‘CONSENT TO OPERATE’ for total value of assets of Rs. 18.75 cr. now, the project proponent has submitted CA certificate mentioning total value of assets as Rs. 188.38 cr. the project proponent is required to intimate the reason for such huge increase in the value of assets. 2. The project proponent has not deposited consent fee adequate for five years. As such, the project proponent is required to clarify regarding above within 03 days, so that further action may be taken in the matter, please.
Date Created: 2022-12-05 11:21:37.251
File Note:
Inspection: false
Inspection Note:
Officer: PPCB128
Reject: false
Reject Note:
Role: RO AEE Arshdeep Singh