Show ApplicationProcessingDetails

Id: 20689714
Approve: false
Approve Note:
Clarification: true
Clarification Note: The application was scrutinized and observed that the industry has not submitted completion certificate from PSCST, Chd for APCD installed with side hood suction system for induction furnaces which are of capacity more than 1TPH. The industry has also not submitted feasibility report/ completion certificate of the sewerage Treatment Plant installed by the industry with the application. You are requested to submit the same within 02 days.
Date Created: 2022-12-20 15:47:14.741
File Note:
Inspection: false
Inspection Note:
Officer: PPCB085
Reject: false
Reject Note:
Role: RO AEE JATINDER SONI