Show ApplicationProcessingDetails

Id: 20782729
Approve: false
Approve Note:
Clarification: true
Clarification Note: The application of the project proponent has been scrutinized and it was observed as under: 1. The project proponent needs to submit status of progress regarding Pond Adoption and its maintenance in Village Bakarpur, Mohali, Distt. SAS Nagar, Punjab. 2. The project proponent has not linked consent fee with the application. 3. The project proponent needs to submit latest status of installation of STP of 6 MLD capacity. You are therefore requested to attend the clarification within 2 days.
Date Created: 2023-01-02 16:42:31.851
File Note:
Inspection: false
Inspection Note:
Officer: PPCB114
Reject: false
Reject Note:
Role: RO AEE Piyush Jindal