| Id: | 20840438 |
| Approve: | false |
| Approve Note: | |
| Clarification: | true |
| Clarification Note: | the application of the project proponent was scrutinized and it has been observed as under: 1. The project proponent has uploaded a copy of CA certificate mentioning the cost of assets as on 31.03.2021, which is not latest. As such, the pp is required upload a copy of latest CA certificate. 2. Adequacy of consent fee can be adjudged after submission of 1 above. Please clarify regarding above within 02 days, so that further action may be taken in the matter. |
| Date Created: | 2023-01-09 16:53:59.298 |
| File Note: | |
| Inspection: | false |
| Inspection Note: | |
| Officer: | PPCB128 |
| Reject: | false |
| Reject Note: | |
| Role: | RO AEE Arshdeep Singh |