<p class="MsoNormal"><span lang="EN-US">It is submitted that the industry is a <span style="mso-spacerun: yes;"> </span>small scale red category unit and has applied for fresh consent to operate under the Water Act ,1974 and under the Air Act ,1981 through OCMMS . Earlier, <span style="mso-spacerun: yes;"> </span>the<span style="mso-spacerun: yes;"> </span>Directions u/s 33 -A of the Water Act ,1974 was issued to the PSPCL authorities to disconnect the electric connection of the industry vide Board letter no 7144 dated 24.11.22 <span style="color: black; mso-themecolor: text1;">as the industry was running without consent and has not made any agreement with the CETP operator and found disposing its effluent in un authorized manner </span>.<span style="mso-spacerun: yes;"> </span>Now the industry has applied fresh consent to operate under the Water Act ,1974 and the industry has deposited consent fees of Rs 14000 vide R.NO CBINH23002445861 dated 2.01.23 under the Water Act ,1974 adequate upto 4.2.27 <span style="mso-spacerun: yes;"> </span>and Rs 8400 vide R.NO CBINH22346852296 dated 2.01.23 under the Air Act ,1981 <span style="mso-spacerun: yes;"> </span>adequate upto 4.2.26<span style="mso-spacerun: yes;"> </span>. </span></p>
<p class="MsoNormal"><span lang="EN-US">To verify the facts ,the industry was visited by the undersigned on 12.01.23 and it was observed as under ;</span></p>
<p class="MsoNormal"><span lang="EN-US">1 .The industry was not in operation during visit and electric connection of the industry has been found disconnect vide TDCO no 1802 dated 26.12.22 </span></p>
<p class="MsoNormal"><span lang="EN-US">2 . The industry is engaged in electroplating process and has made agreement with the CETP operator i.e JBR Unit 1 @3000 Litre/month dated 21.09.22 <span style="mso-spacerun: yes;"> </span>. </span></p>
<p class="MsoNormal"><span lang="EN-US">3 . The industry has installed the new water meter and has started maintaining the record of daily water consumption viz a viz effluent lifted .</span></p>
<p class="MsoNormal"><span lang="EN-US">4 . The industry has submitted electricity bill dated 04.2.2020 as proof of the date of the commissioning of the industry . The industry is surrounded by various other industrial units, having valid consents from the Board. Hence the site is suitable for establishment of red category unit.</span></p>
<p class="MsoNormal"><span lang="EN-US">5 . It is intimated that the subject cited industry has made fresh agreement with JBR on 21.09.2022. As, the treatment capacity of M/s JBR was almost exhausted. Accordingly, on 11.09.2020, the Board has directed CETP Operator that no new/revised agreements are made without CTE/CTO of the Board. Now, a new CETP for electroplating unit has been recently commissioned at Chanalon and total available treatment capacity of M/s JBR is 77 KLD.</span></p>
<p class="MsoNormal"><span lang="EN-US">6 . No DG set has been installed by the industry . </span></p>
<p class="MsoNormal"><span lang="EN-US">In view of above , it is recommended that consent to operate under the Water (Prevention & Control of Pollution) Act, 1974 and under the Air (Prevention & Control of Pollution) Act, 1981 may be granted to industry <span style="mso-spacerun: yes;"> </span>for six months along with temporary restoration of electric connection for six months with suitable conditions, please.</span></p>
<p class="MsoNormal"><span lang="EN-US"> </span>The competency to decide the application lies with Hon’ble Chairman of the Board.</p>