| File Note: | <p>The industry was granted water consent on 14/12/2021 subject to certain conditions mentioned therein. Ro has recommended the case for grant of long time renewal of Water consent with out carrying the monitoring of ETP. If approved the case be returned to Ro to explain the reasons why the case has been recommended for long time consent? Also direct all the AEE 's to process the application insight of prevailing policy of the Board, please. </p> |
| Inspection: | false |
| Inspection Note: | |
| Officer: | PPCB031 |
| Reject: | false |
| Reject Note: | |
| Role: | ZO EE Om Parkash |