Date Created: 2023-01-27 09:49:46.415
File Note: <p>It is submitted that the representative of the industry has informed &nbsp;that the boiler of 10TPH will be installed instead of 40 TPH as mentioned in application form.Further , the init has not submitted the feasibility report of the APCDs.</p> <p>Therefore, the case needs to be returned.(</p>