<p>1} As pointed by EE, ZO......besides giving classification of area and providing requiste certificate from concerned authority, RO to check</p>
<p>i). In one of the process, powder is sprinkled while mfg. tubes and lot of dust emissions are generated. What arrangements industry has made to control the same.</p>
<p>ii). As industry has 3TPH boiler and if it is operated for 8 hr, water requirement for boiler alone will be 24 KLD. Whereas industry has filled only 6 KL of water for all purposes. In case indirect steam through coil system is being used, then condensate recovery status is required to be provided. </p>
<p>iii) If (ii) is not applicable, then quantity of steam lose, higher water consumption from boiler section and possibility of condensate going to drain will be there. </p>
<p>iv) In addition to waste condensate, boiler blow down is also likely to be generated from boiler section. Further, after tube making, it is dipped in water for checking leakage specifically valve/ tuti leakage. After some time the waste water from here is to be discargded. Likewise, purge waste water from cooling/ recirculation may also be there. Therefore, we can't say that TE is nil.</p>
<p>RO to check and report through return reply by 30.1.2023, please 1} As pointed by EE, ZO......besides giving classification of area and providing requiste certificate from concerned authority, RO to check</p>
<p>i). In one of the process, powder is sprinkled while mfg. tubes and lot of dust emissions are generated. What arrangements industry has made to control the same.</p>
<p>ii). As industry has 3TPH boiler and if it is operated for 8 hr, water requirement for boiler alone will be 24 KLD. Whereas industry has filled only 6 KL of water for all purposes. In case indirect steam through coil system is being used, then condensate recovery status is required to be provided. </p>
<p>iii) If (ii) is not applicable, then quantity of steam lose, higher water consumption from boiler section and possibility of condensate going to drain will be there. </p>
<p>iv) In addition to waste condensate, boiler blow down is also likely to be generated from boiler section. Further, after tube making, it is dipped in water for checking leakage specifically valve/ tuti leakage. After some time the waste water from here is to be discargded. Likewise, purge waste water from cooling/ recirculation may also be there. Therefore, we can't say that TE is nil.</p>
<p>RO to check and report through return reply </p> |