Show ApplicationProcessingDetails

Id: 21141386
Approve: false
Approve Note:
Clarification: true
Clarification Note: The application of the industry was scrutinized and it was observed as under:- 1. The industry has been established without obtaining the CTE of the Board. The industry obtained electricity load on 15/03/2019 and as such, the fees are required to submit the consent fee accordingly. 2. The industry has applied for fresh Consent to Operate under Water (Prevention & Control of Pollution) Act, 1974 but has not applied for Consent to Operate under the Air (Prevention & Control of Pollution) Act, 1981. The industry is also requested to submit the Site plan and approved Building plan and clarify the above so that further action in the matter may be taken.
Date Created: 2023-02-13 12:20:48.875
File Note:
Inspection: false
Inspection Note:
Officer: PPCB158
Reject: false
Reject Note:
Role: RO AEE Rozert Dhamija