Show ApplicationProcessingDetails

Id: 21150433
Approve: false
Approve Note:
Clarification: false
Clarification Note:
Date Created: 2023-02-13 16:42:47.235
File Note: <p>As discussed with SEE ZO-2, the cost of plant and machinery is 7.65 cr as per project report and the industry has applied under small scale ,but as per the policy of the Board the industry falls under Medium Scale and the competancy to decide the case is Chief Environmenatal Engineer. Therefore, the application may be forwarded to CEE of the Board for grant of NOC as per note above.&nbsp;</p>
Inspection: false
Inspection Note:
Officer: PPCB102
Reject: false
Reject Note:
Role: RO AEE Gurkaran Singh