<p>Pl clarify the following -</p>
<p> </p>
<p> 1. Who visited the industry.</p>
<p> </p>
<p>2. Whether the unit has been established in the land for which it was granted CTE. Kindly confirm.</p>
<p> </p>
<p>3. Whether the unit has planted thick plantation of spreading crown varieties of evergreen trees all along the boundary wall of the rice sheller.</p>
<p> </p>
<p>4. Whether all dust emitting points have been properly hooded and dust extracted to a common point. </p>
<p> </p>
<p>5. Whether adequate stack heights and sampling arrangements have been provided with APCDs.</p>
<p> </p>
<p>6. How will the unit manage/handle and dispose off the ash to be generated from dryer furnace.</p>