Show ApplicationProcessingDetails

Id: 21203111
Approve: false
Approve Note:
Clarification: true
Clarification Note: Application of the industry has been scrutinized and it is observed as under:- 1) The industry has not submitted feasibility report regarding installation of additional boiler as well as Air pollution control device to be installed. 2) As per CA certificate submitted earlier as son 31.03.2019, the value of land is mentioned as 33.20 lakhs however as per CA certificate as on 31.03.2022, the value of land is mentioned as 38.93 lakhs. Kindly clarify above, within 02 days.
Date Created: 2023-02-20 14:25:12.52
File Note:
Inspection: false
Inspection Note:
Officer: PPCB146
Reject: false
Reject Note:
Role: RO AEE Amandeep Singh