| File Note: |
<p>Case receieved on 21.02.2023 at 2.31 PM and JEE visited the site and process the case by 5.31 PM on same day. I think JEE was in hurry and failed to report vital things</p>
<p>1. No agenda note found attached.</p>
<p>2. Status of electric disconnection.</p>
<p>3. Status w.r.t distance from residential area. </p>
<p>4. State Govt Project for which the RMC is being installed and what public interest is involved</p>
<p>5. Date of start and completeion of project...</p>
<p>6. Whether Mandi Board has given the permission. If so what is the validity of the permission.</p>
<p>7. As RMC is in dana Mandi, what will be its effect on nearby sorrounding. </p>
<p>8. What is the status of Air pollution control Arrangments, with respect to </p>
<p>a). Storage of raw material like sand, cinder, coarse agrregate....</p>
<p>b). Cement storage area.....</p>
<p>c). Effluent generated from washing of mixers and equipment, treatment and disposal arrangements..</p>
<p>Submit comments/ recommendations through return reply</p>