Show ApplicationProcessingDetails

Id: 21318464
Approve: false
Approve Note:
Clarification: true
Clarification Note: As desired by the competent authority, in the project report, it is mentioned that the project will be installed in 2 phases. In 2nd phase vacuum induction melting has been proposed. It is requested to elaborate on it.
Date Created: 2023-03-03 11:01:28.983
File Note:
Inspection: false
Inspection Note:
Officer: PPCB102
Reject: false
Reject Note:
Role: RO AEE Gurkaran Singh