Show ApplicationProcessingDetails

Id: 21396565
Approve: false
Approve Note:
Clarification: false
Clarification Note:
Date Created: 2023-03-12 16:31:42.294
File Note: <p style="text-align: justify;">It is intimated that the reply submitted by the industry was verified by RO, as per the report the PP has not installed a Water meter on the freshwater used in the surface treatment process. The industry has not made adequate storage to handle the trade effluent generated from the process.&nbsp; So The reply submitted by the industry is not satisfactory. The application is pending since 8/2/23.</p> <p style="text-align: justify;">May if approved CTO under the Water Act,1974 applied by the industry be refused. EE, RO may also be requested to send the further recommendation through e-note, please.</p> <p style="text-align: justify;">( Competency: SEE)</p> <p style="text-align: justify;">&nbsp;</p>
Inspection: false
Inspection Note:
Officer: PPCB054
Reject: false
Reject Note:
Role: ZO EE Kuldeep Singh