| Id: | 21409330 |
| Approve: | false |
| Approve Note: | |
| Clarification: | true |
| Clarification Note: | The application of the industry has scrutinized and it is observed as under:- 1. The industry is required to submit site plan approved by the Director of Factory, Punjab. 2. The industry is required to all the documents duly signed by the authorized signatory (Compliance in annotated Form, Feasibility report of APCD with proposed paint booths and the project report). You are requested to submit above said observations within 02 days. |
| Date Created: | 2023-03-13 17:27:52.158 |
| File Note: | |
| Inspection: | false |
| Inspection Note: | |
| Officer: | PPCB142 |
| Reject: | false |
| Reject Note: | |
| Role: | RO AEE Gurinderpal Singh |