File Note: <p>&nbsp;1. Issue SCN&nbsp; to industry with hearing on 14.03.2023 due to expansion of unit..........Production and capacity of furnaces ...increased from 90 T to 160 T .......But no latest&nbsp;&nbsp;document for confirmation of siting guidelines submitted.</p> <p>2.&nbsp; &nbsp;Call explaination of concerned AEE for conceiling the facts and for sending the case without verification of siting guidelines</p> <p>3.&nbsp; Copy to EE, RO, LDH for not examing the case properly&nbsp; before sending to ZO.&nbsp;</p> <p>4.&nbsp; RO to give comments regarding fullfillment of siting guidelines as per physical visit and with documentry proof from competent authority</p> <p>&nbsp;</p>
Inspection: false
Inspection Note:
Officer: PPCB032
Reject: false
Reject Note:
Role: ZO SEE R K Ratra