| Clarification Note: |
It is requested to provide following within 2 days positively so that a comprehensive case may be presented to higher authorities:
1. A final target date of completion of STP rehabilation project.
2. The date by which the rehabilitated STP will be stabilized and start giving desired results so that sampling process can be started.
3. Pert chart (stage/ component/ activity wise ) of rehablitation and stabilzation of STP.
4. Can't allow treated effluent discharge into river Satluj for indefinite time . Proposal for reutization of treated effluent.
5. Compliance of PPCB directions to deposit Environment Compensation.
|