| Id: | 21592457 |
| Approve: | false |
| Approve Note: | |
| Clarification: | true |
| Clarification Note: | Application of the HCF was scrutinized and following was observed that the HCF has mentioned mode of disposal of the treated effluent after STP in application form. However, the HCF has not submitted document regarding permission of sewer issued from concerned authority. It is requested to submit document regarding permission of sewer issued from concerned authority within 02-days so that your application may be processed. |
| Date Created: | 2023-03-28 15:36:52.082 |
| File Note: | |
| Inspection: | false |
| Inspection Note: | |
| Officer: | PPCB122 |
| Reject: | false |
| Reject Note: | |
| Role: | RO AEE Vinod Kumar |