Show ApplicationProcessingDetails

Id: 21727096
Approve: false
Approve Note:
Clarification: true
Clarification Note: The application of the industry has been scrutinized and observed that in DTP letter it is mentioned that the electric line of 11 KV high tension wire is crossing in the site, which required to be removed. However, the industry has not submitted any document regarding the same. As such, you are requested to clarify the aforesaid observation within 02 days, so as to proceed further in the matter. Till then, the application submitted by the industry shall be treated as incomplete.
Date Created: 2023-04-10 10:59:02.585
File Note:
Inspection: false
Inspection Note:
Officer: PPCB143
Reject: false
Reject Note:
Role: RO AEE Mohit Singla