File Note: <p>Sir in the EC earlier granted to the industry, two aspects have been mentioned by the competent authority i.e no of furnaces and the production capacity i.e 115500 TPA.</p> <p>Now the proposal of the industry for single furnace has been accepted by the competent authority with same production capacity with single 30 T furnace.</p> <p>Considering the production capacity mentioned in previous as well as ammended EC, condition holds good.</p> <p>Submitted please.</p> <p>&nbsp;</p>