Show ApplicationProcessingDetails

Id: 21732799
Approve: false
Approve Note:
Clarification: false
Clarification Note:
Date Created: 2023-04-10 13:56:24.886
File Note: <p>The reply of SCN submitted by the industry has been deatiled by AEE in his note dated 31/03/2023.</p> <p>As per current verification, the industry is having production capacity less than 90 T/ day and it has dropped the proposal to increase the production upto 120 T/ day and requested to grant renewal of consent to operate for production upto 90 T/ day.</p> <p>But, the subject cited case is for obtaining varied CTO upto 120 T/ day, therefore, it is required to be returned and the industry will be requested to apply for renewal of CTOs.</p> <p>In view of the above facts, it is recommended that the subject cited case may be allowed to return to the industry.</p> <p>&nbsp;</p>
Inspection: false
Inspection Note:
Officer: PPCB073
Reject: false
Reject Note:
Role: RO EE Anuradha Sharma