| File Note: |
<p>1. As per field report, the industry has installed machinery of 1:6. It is a new unit and we require low liquor ratio machine.</p>
<p>2. As per proposal recieved from RO, the industry has proposed 6 baths for cotton dyeing, which is on very lower side.</p>
<p>3. No report of steam condensate or cooling water recovery is submitted.</p>
<p>4. No report regarding installation of EMF at the water supply source or at the outlet of ETP submitted. Relevant columns lying blank.</p>
<p>5. No report about installation of seperate energy meter with ETP or APCD given. Columns lying blank in agenda note.</p>
<p>6. No report of CCTV camera to be provided at fuel Feeding point or facing to stack given</p>
<p>7. No report regarding adequate arrangement for hazardous waste and submission of authorization application submitted.Columns lying blank in agenda note</p>
<p>8. For 95 KLD effluent, 5300 sq yard land....What is the rate of application and whether it is adequate for all seasons including winter.</p>
<p>9. No report of fly ash arrangements. .</p>
<p>During discussions with CEE also, it was decided to send reports on some of the bove issues in all cases.But the discussions are ignored.</p>
<p>Case is sent in hurry. Call the explanation of AEE for providing incomplete report </p>
<p>Submit point wise reply immediately</p>