Show ApplicationProcessingDetails

Id: 21801983
Approve: false
Approve Note:
Clarification: true
Clarification Note: The application of the institute was scrutinized and it has been observed that:- 1. The institute has not mentioned the date of commissioning of the college campus/ hostel at the mentioned site i.e. Dandi Swami Road, Ludhiana. 2. The consent fee deposited by the institute is not adequate. It is therefore requested to submit he reply within 02 days.
Date Created: 2023-04-18 10:57:08.964
File Note:
Inspection: false
Inspection Note:
Officer: PPCB150
Reject: false
Reject Note:
Role: RO AEE Bhisham