| Clarification Note: |
1. The project proponent has not linked any fee with applicaation.
2. The project proponent has filled trade effluent @ 3.5 KLD and domestic effleunt @ 0.5 KLD in the application form. However, the PP has not submitted any share allotment letter from PAIC regarding discharge of trade effluent and domestic effluent into CETP of Mega Food Park.
3. The project proponent has not submitted any detail regarding treatment/disposal of solid waste to be generated from its premises.
4. The project proponent has submitted detail of D.G. set as NIL. It is practically not possible to run a food processing industry without D.G. set. The project proponent is required to submit detail of D.G. sets to be installed by it.
|