File Note: <p>The pointwise reply to the observations raised is as under : -</p> <p>1. As the indsutry has already enchanced the production capacity, machinery and there is no increase in the land area and building, there is no increase in fixed assets.&nbsp;</p> <p>2. The industry has updated its APCDs and APCDs are now adequate to handle&nbsp; extra pollution load. The sampling of the same shall be carried out coming season.</p> <p>3. As the site falls outside MC limit of Malout and thus the site is suitable for carried out expansion.</p> <p>Submitted for approval please.</p>