Show ApplicationProcessingDetails

Id: 22771328
Approve: false
Approve Note:
Clarification: true
Clarification Note:
Date Created: 2023-07-09 23:02:26.587
File Note: <p>As per decision of hearing dated 10-01-23, it eas decided that Industry shalld evelop adequate plantation area for disposal of treated effluent.&nbsp;</p> <p>As per CTO application, industry has filled that out of 48 KLD consumption, 8.5 KLD effluent will be generated. However as per agenda note , only 3 KLD is effluent is discharged on to land for plantation. Whether industry has developed adequate land for disposal of effluent at optimum capacity .</p> <p>SCN be issued with Hearing with a direction to submit water balance statement reg consumption and discharge of effluent giving&nbsp; details and adequay of plantation area .&nbsp;</p>
Inspection: false
Inspection Note:
Officer: PPCB017
Reject: false
Reject Note:
Role: CEE Sandeep Bahl