| Clarification Note: | Furnace is under installation. APCD in form of bag filter house is installed, however hood is yet to be installed. It will take 3-4 months for completion of project. In addition to this, Cable laying and 66 KV connection by PSPCL is delayed leading to delay in our project. |
| Date Created: | 2023-07-11 10:51:46.154 |
| File Note: | Furnace is under installation. APCD in form of bag filter house is installed, however hood is yet to be installed. It will take 3-4 months for completion of project. In addition to this, Cable laying and 66 KV connection by PSPCL is delayed leading to delay in our project. |