Show ApplicationProcessingDetails

Id: 23689710
Approve: false
Approve Note:
Clarification: false
Clarification Note:
Date Created: 2023-09-22 17:53:32.56
File Note: <p>It is submitted that the updatedconstruction status of the CETP as per the PERT chart is attached herewith as annexure-A.&nbsp;</p> <p>Further, the activities which have not yet been completed as per the schedule of the PERT chart, have been marked in RED colour boxes.</p> <p>submitted please.</p>
Inspection: false
Inspection Note:
Officer: PPCB128
Reject: false
Reject Note:
Role: RO AEE Arshdeep Singh