| Id: | 23689800 |
| Approve: | false |
| Approve Note: | |
| Clarification: | true |
| Clarification Note: | On scrutinizing the application, it was observed as under:- 1. The industry is required to submit land use classification of the site as per existing Master Plan/ LPA of the area. 2. The industry is required to submit feasibility report-cum-completion certificate regarding the adequacy of air pollution control devices provided for arresting emissions of plant operating at enhanced capacity. Clarify within 2 days. |
| Date Created: | 2023-09-22 18:00:08.103 |
| File Note: | |
| Inspection: | false |
| Inspection Note: | |
| Officer: | PPCB149 |
| Reject: | false |
| Reject Note: | |
| Role: | RO AEE Anish Sharma |