| File Note: |
<p><span style="font-size: 13.5pt; line-height: 115%; font-family: 'Segoe UI', 'sans-serif';">EE ZO has observed that RO has not mentioned about NOC regularization Fee, the total area of the project, adequacy of consent fee, CA certificate differs by mentioning total amount as Rs. 2.06 Crore yet the RO mentioned the total value as Rs. 9.95 crore, not submitted approved site plan of the colony issued from Chief Town Planner, Punjab, Chandigarh, the residential colony has not submitted NOC from the Gram Panchayat, Nausshera for the discharge of surplus water, not mentioned about the Enviornmental Clearance, total area for the discharge of treated domestic effluent and not applied for CTO under Air Act. Hence, SCN for refusal of CTO under Water Act may be issued for 07-days, please.</span></p> |