
| Id: | 24823611 |
| Approve: | false |
| Approve Note: | |
| Clarification: | true |
| Clarification Note: | Moreover, the industry is yet to submit following documents:- 1. The industry is required to submit proof of date of commissioning of the unit so that requisite fee can be calculated. 2. The fee deposited by the industry is not adequate considering the registry documents. As such, it is requested to deposit the adequate from year 2010 to next five years. |
| Date Created: | 2024-01-31 10:48:55.625 |
| File Note: | |
| Inspection: | false |
| Inspection Note: | |
| Officer: | PPCB142 |
| Reject: | false |
| Reject Note: | |
| Role: | RO AEE Gurinderpal Singh |