Date Created: 2024-02-01 12:55:33.248
File Note: Sir, it is submitted that the Punjab State Council for Science & Technology has issued Completion certificate vide letter no PSCST/TFD/393 dated 14.09.2023 as per which installed induction furnace is of 8 TPH capacity and it seems that production capacity will be 8 x 16 heat x 300 days = 38400 Ton/year which cover under Environmental Clearance and Regional Office recommended to consider consent with condition that the industry shall obtain the Environmental Clearance in time bound manner. In view of the above, it is recommended that consent application may be returned to industry with request that the industry shall obtain Environmental Clearance as required under EIA Notification, 2006 before commissioning of induction furnace of 8 TPH capacity, please.
Inspection: false
Inspection Note:
Officer: PPCB056
Reject: false
Reject Note:
Role: ZO EE Pardeep Balu