Id: 25023637
Approve: false
Approve Note:
Clarification: false
Clarification Note:
Date Created: 2024-02-28 07:56:22.782
File Note: As per above report,it was observed that the PP has submitted approved building plan as such no requirement of certificate for suitability as mentioned by you and consider commissioning proof from date of approval of building plan . Moreover you have raised clarification after 20 days so explain your position for taking 20 days for raising clarification on case ?
Inspection: false
Inspection Note:
Officer: PPCB109
Reject: false
Reject Note:
Role: RO EE Daljit Singh