| File Note: |
The project proponent has applied for fresh consent to establish under the provisions of Water (Prevention & Control of Pollution) Act, 1974 and Air (Prevention & Control of Pollution) Act, 1981 for Dismantling of Electronic Waste ( Electronic & Medical Equipments )@ 3 MTD along with requisite document.
The project proponent has submitted brief project report with the value of proposed project report is Rs. 40 lakh. The project proponent has deposited Rs. 4100/- vide R no. 950743291 dated 24.02.2024 as NOC fee, which is adequate for one year.
The project proponent has submitted change in constitution of Industrial Plot no. 272,Phase-IX, Industrial Focal Point, Mohali in name of 1) Smt. Neeraj Bhandari, 2) Sh. Vinod Bhandari issued by PSIEC. The project proponent has also submitted transfer of industrial plot for manufacturing of Hydraulde Powerpad, Hardrolic Electrical issued by PSIEC vide no. 16607 dated 09.03.2010.
The project proponent has submitted rent agreement between Sh. Vinod Kumar and TNI-INC Solutions Pvt. Ltd., which is valid for 11 months. The project proponent has submitted Memorandum of Association of TNC-INC Solutions Private Limited. The project proponent has submitted building plan stamped by Competent person department of Director of Factory, Punjab.
The project proponent has submitted feasibility report, as per which the industrial unit shall not use water for any production related activity. Therefore there will be no trade effluent generation. To meet drinking, cooking, washing, and sanitation requirements of the workers, about 0.5 m3/day of fresh water will be needed. This will result in generation of 0.4 m3 /day of domestic effluent. Domestic effluent will be discharged into sewer line.
The whole process is carried in manually and only shredding machine will be used for the shredding purposes and dust collector & filter bag house will be used as air pollution control system. There is no installation of D.G set.
The site was visited by the officer of the Board on 06.03.2024 and during visit it was observed as under:
1. The industry has proposed to install Dismantling of Electronic Waste unit in the said plot.
2. The industry has not installed any machinery in the existing shed.
3. The industry is located in Industrial Focal Point, which is prescribed for this type of industry.
The site is suitable for establishment of this type of industry.
In view of above, it is recommended that the consent to establish under the provisions of Water (Prevention & Control of Pollution) Act, 1974 and Air (Prevention & Control of Pollution) Act, 1981 may be granted for one year with special conditions as under:
1. The industry shall not start any other new process without the prior written permission of the Board.
2. The industry shall not generate any trade effluent.
3. The industry shall obtain permission from other concern departments, if need be.
*Competency – Senior Environmental Engineer
(Deemed Approved): - 27.03.2024
|