| Id: | 25124141 |
| Approve: | false |
| Approve Note: | |
| Clarification: | false |
| Clarification Note: | |
| Date Created: | 2024-03-11 14:49:31.703 |
| File Note: | Sir, it is submitted that interim environmental compensation of Rs. 1.50 Lacs was imposed on the industry. The industry has deposited Rs. 25000/- as EC out of total Rs. 1.50 Lacs & submitted written request that the rest of the amount of EC may be taken in 5 equal installments as it is not in a financial position to deposit full amount of EC immediately. Further, the payment of EC in six installments has not been approved by competent Authority. Submitted please. |
| Inspection: | false |
| Inspection Note: | |
| Officer: | PPCB052 |
| Reject: | false |
| Reject Note: | |
| Role: | RO EE Ravinder Bhatti |