| File Note: |
Sir, the point wise reply is as under-
1. Due to the non availability of technical staff, air sampling could not be carried out.
2. The industry has compacted the soil and make it stabilized, however, surface carpeting not provided and same will be provided within one month as per assurance given by industry through undertaking.
3. The industry has provided adequate plantation along boundary wall and HDPE wrap knitted fabric over rice husk.
4. The industry has provided separate cyclone seperators with shelling section as well as dryer section alongwith the sampling arrangements.
In view of above, it is recommended that consent to operate granted under the Water Act, 1974 & the Air Act, 1981 may both be granted upto 30/09/2028 (upto adequacy of fee) for manufacturing of Sorted Raw Rice (with dryer) @ 2.0 TPH by processing of Paddy @ 3.0 TPH, as raw material under orange category, subject to certain conditions to be mentioned therein and with a special conditions-
1. The industry will got analyzed its stack emission samples from Board's lab or Board's approved lab in this season.
2. The industry shall stabilize the movement area within one month and shall submit the compliance thereafter immediately.
|