| Id: | 25229134 |
| Approve: | false |
| Approve Note: | |
| Clarification: | false |
| Clarification Note: | |
| Date Created: | 2024-03-22 10:18:43.138 |
| File Note: | It is submitted that the reply of clarification may kindly be perused in the note of AEE. RO submitted that the capacity of terminal STP of MC Kurali is 5 MLD and the average inflow of sewage is about 4-4.5 MLD. Further, the project proponent has not proposed development of plantation as per Karnal technology and excess treated wastewater after utilisation in flushing and green area, will be discharged into MC sewer. Submitted for approval of action already recommended please. |
| Inspection: | false |
| Inspection Note: | |
| Officer: | PPCB051 |
| Reject: | false |
| Reject Note: | |
| Role: | ZO EE Rajeev Gupta |