| File Note: | Sir, the industry was visited by undersigned on 20.03.2024 alongwith staff from Air Lab and it was found that the unit was not operational due to power cut. Therefore air emission sampling couldn't be carried out. Since, the industry has also not submitted reply to clarification raised on the application. It is therefore requested that application of the industry be returned back to avoid un-necessary delay. |