| Clarification Note: |
The point wise reply is as under:-
1. The detail of addition of machinery for Rs. 184.17 is attached here and NOC fee already deposited.
2. We are submitting the details of receipts of 169200/-.
3. We are submitting the analysis report of stack emission.
4. The Govt. of Punjab Department of Science & Technology & Environment vide notification no. 10/64/2020-STE4/469 dated 04.10.2023 in which mention that furnace oil & any other liquid oil containing high sulphur contents (Exceeding 1.8% by weight) shall not be allowed to used as fuel, but we are using upto max. 1.8% in our unit (bill of furnace oil is attached) containing oil %.
5. We are submitting revised compliance report.
It is also submitted that our ZLD plant as gone under break down w.e.f. 31.03.2024 due to heat exchanger damage. It will take 15-20 days for replace and repair. This is for your information and necessary action please.
It is also noted that due to some clerical mistake, we have revised company profile name M/s Nicks India Tools Pvt. Ltd., Village Khakhat, Sua Road, G.T Road, Ludhiana instead of Nicks India Tools Private Limited unit-4, Village Khakhat, Sua Road, G.T Road, Ludhiana. Please make necessary correction in your records.
|
| File Note: |
The point wise reply is as under:-
1. The detail of addition of machinery for Rs. 184.17 is attached here and NOC fee already deposited.
2. We are submitting the details of receipts of 169200/-.
3. We are submitting the analysis report of stack emission.
4. The Govt. of Punjab Department of Science & Technology & Environment vide notification no. 10/64/2020-STE4/469 dated 04.10.2023 in which mention that furnace oil & any other liquid oil containing high sulphur contents (Exceeding 1.8% by weight) shall not be allowed to used as fuel, but we are using upto max. 1.8% in our unit (bill of furnace oil is attached) containing oil %.
5. We are submitting revised compliance report.
It is also submitted that our ZLD plant as gone under break down w.e.f. 31.03.2024 due to heat exchanger damage. It will take 15-20 days for replace and repair. This is for your information and necessary action please.
It is also noted that due to some clerical mistake, we have revised company profile name M/s Nicks India Tools Pvt. Ltd., Village Khakhat, Sua Road, G.T Road, Ludhiana instead of Nicks India Tools Private Limited unit-4, Village Khakhat, Sua Road, G.T Road, Ludhiana. Please make necessary correction in your records.
|