| Clarification Note: |
On Scrutinizing the application of the project proponent and it was observed as under:
1. In the application form, the project proponent has mentioned total project cost Rs. 81.75 crore. But the project proponent has submitted CA certificate with the value of fixed assets of Rs. 139.40 crore, please clarify.
2. The project proponent has not submitted analysis report of outlet of STP.
3. The project proponent has not deposited/ link consent fee with the application.
You are therefore requested to submit reply of the above said observation within 2 days.
|