| File Note: |
As discussed, it is submitted that the industry was visited by undersigned on 28.03.2024 and it was observed as under:-
1) The industry was in operation, with saila section on one shelling line, steamed section on other shelling line and solvent extraction plan. Refinery unit was not in operation as per demand.
2) During visit to the industry on 08.12.2023, it was observed that the industry has not provided stack of adequate height and with adequate arrangements for carrying out emission sampling at the paddy pre cleaner section as well as shelling section and the industry was advised to rectify the same. However, during visit to the industry on 28.03.2024, no compliance w.r.t. to above observation was observed.
3) The industry has installed common ETP consisting of components -Screen Chamber, Oil & Grease Trap, Equalization Tank with Air Diffuser (I&II), Tube Settler, Buffer Tank, UASB Reactor, Secondary Clarifier, Aeration Tank with Air Diffuser System, Clarifier, Filter Fired Tank, Hypo Dosing, Pressure Sand Filter and Activated Carbon Filter. For sludge treatment, sludge holing taking with diffuser, sludge feed pump & centrifuge.
However, during the visit, the ETP was in operation with components collection-cum-equalization tank Screen Chamber Oil & Grease Trap Equalization Tank with Air Diffuser (I&II) Tube Settler Pressure sand filter Activated Carbon Filter Outlet
Effluent samples were collected from the outlet of ETP as well as aeration tank of ETP for analysis.
4) The industry is required to submit record of fresh water consumption as well as effluent generation / treatment.
5) The industry has provided plantation in an area of about 2.5 acres however vegetation / weeds were found grown in the plantation and the same is required to be cleaned / maintained.
In view of above, since the analysis report of the industry is awaited and further the industry is required to submit compliance of above observations, it is therefore recommended that the consent applications of the industry may be returned (from the portal of your goodself) with the advise to resubmit the application with compliance of the above observations as well as sample analysis report / charges carried out by the Board.
|